Technical Parameters
Components Qty | 22 parts |
Cycle Time | 3 sec/pc |
Weight | About 1500kg |
OEE | 80% |
First Pass Yield | 98% |
Standard Parts Brand | Siemens PLC, HMI, Motor, Festo pneumatic, MISUMI guide rail |
Requested Operators | 5 operators for heating sub loading, 1 operator operates the line. |
Certificate | CE |
1) PLC control system.
2) Automatic feeding and assembly of base, sleeve, left the terminal, right terminal, middle terminal, spacer, baffle, spring, frame, cover, and other parts. and automatic locking screws.
3)Automatically detect the presence or absence of parts, conduct plugging force test, and unload qualified and unqualified products respectively. And check the shutter bounce.
4) Automatic detection, with or without material start and stop.
5) Automatic counting and output setting.
6) Touch screen, easy and safe operation.
7) Automatic alarm for abnormal shutdown and report abnormal information.
Machine Feature
Company Advantages
· Yicheng assembly equipment manufacturers is designed under the guidance of highly skilled designers.
· Yicheng employs professional quality check team to test the quality of the product.
· Dongguan Yicheng Automation Equipment Co.,Ltd.'s productive service team is able to provide better customer service.
Company Features
· Dongguan Yicheng Automation Equipment Co.,Ltd. is professional in producing including assembly equipment manufacturers.
· The product quality and service requirements are almost extreme for Yicheng Automation.
· The decisive determination of Yicheng is to supply the best customer service. Inquire!
Application of the Product
The assembly equipment manufacturers produced by Yicheng Automation has a wide range of applications.
Our company will modify and adjust the original solution according to the customer's needs. By doing so, we can provide solutions that best meet the customer's needs.
After we complete the assembly and debugging of the equipment, we will inspect and select appropriate packaging materials to protect the equipment from shock, moisture, and fixation.
Make sure the equipment reaches its destination in good condition.
● On site installation, debugging, training and mass production follow up.
● 1 year Warranty from date of shipment, lifetime maintenance service.
● Response any defects claims within 4 hours for mainland customers.
● 12 hours for overseas customers by telephone or mail.
● Supply remote services by smart glass, team viewer, Teams and camera.
1. The technical training described below is free technical training, and no additional fees are charged. The technical training consists of the project's on site general manager, mechanical engineer and electrical engineer, who are responsible for implementing the entire training plan.
2. The whole process of installation from the installation to the commissioning is carried out by the expert group and the production technology, equipment management and production operators designated by the customer. At the same time, the expert group is responsible for technical guidance to the customer's technical staff throughout the implementation process. Training with technical points, including:
a. Equipment system principle and operation method, maintenance.
b. Equipment operation and debugging, parameter setting.
c. Operation and application of the software.
d. Operating procedures and precautions for the equipment.
e. Safety protection measures for various action agencies.
f. Maintenance of electrical systems and mechanical parts.
g. How to make correct judgment, analysis and how to troubleshoot when the equipment fails.
h. Solutions to possible dangerous situations.